Thomas G. Heintzman, O.C., Q.C., FCIArb

What Amounts To An Effective Claim Under A Building Contract?

The Ontario Court of Appeal has recently allowed the appeal in the case of Ledore Investments Limited (Ross Steel Fabricators & Contractors) v. Ellis-Don Construction Ltd., 2017 ONCA 518. In doing so, it held that the arbitrator committed no reviewable error in deciding that the correspondence sent by Ellis-Don to its subcontractor did not amount […]

Continue Reading

May A Party Terminate A Contract For “Fundamental Breach”?

In the recent decision in R.P.M. Investment Corp. v. Lange, 2017 CarswellAlta 770, 2017 ABQB 305, the Alberta Court of Queen’s Bench held that a party to a contract may terminate a contract on the basis of a “fundamental breach” of the contract, in addition to the right to terminate the contract for repudiation. While […]

Continue Reading

When May An Arbitral Tribunal Correct Its Award?

Arbitrators are mortal. They may make mistakes in issuing their awards. In what circumstances may they correct an award? The scope of the authority of an arbitral tribunal to alter its award after the issuance of the award has been examined in a recent Scottish case – NKT Cables A/S v. SP Power Systems Limited, […]

Continue Reading

Supreme Court Of Canada Grants Leave To Appeal In Bond Notification Case

On March 9, 2017, the Supreme Court of Canada granted leave to appeal from the decision of the Alberta Court of Appeal in Valard Construction Ltd. v. Bird Construction Co., 2016 CarswellAlta 1584, 57 C.L.R. (4th) 171. This appeal will be of significance in determining the rights of contractors and subcontractors to receive, and the […]

Continue Reading

Recommendations To Amend Ontario’s Construction Lien Act

On April 30, 2016, a Report was delivered to the Ontario Government proposing amendments to the Ontario Construction Lien Act. This report may, in whole or in part, soon be implemented by the Ontario Legislature. For this reason, those engaged in the construction industry or construction litigation in Ontario must immediately become familiar with the […]

Continue Reading

Contract Limitation Clause Precludes Contractor’s Claim Over Against Designer

The limitation periods which apply to construction claims are difficult to sort out at the best of times. They are even more complicated when the limitation period applies to a claim over for contribution or indemnity. That situation arises when the owner sues the contractor and the contractor then seeks contribution or indemnity from another […]

Continue Reading

New International Commercial Arbitration Act Enacted In Ontario

On March 22, 2017, a new International Commercial Arbitration Act, 2017 came into force in Ontario (the 2017 ICAA). The 2017 ICAA is contained in Schedule 5 to the Burden Reduction Act, 2017, SO 2017, c. 2.. The 2017 ICCA replaces the existing Ontario International Commercial Arbitration Act, RSO 1990, c I.9 (the Old ICAA). […]

Continue Reading

Construction Contract Held To Mandate The Payment Of Extras

One of the most contentious issues in building contracts is mechanism to ensure that the contractor is guaranteed payment for extras, and that the owner is guaranteed not to pay for something that is not an extra. It would be simple to state these propositions in a building contract, but they usually aren’t there. However, […]

Continue Reading

Discovery Of Facts Following Mediation Impacts The Limitation Period: Ontario Court Of Appeal

In 625805 Ontario Ltd. v. Silverwood Flooring Inc., the Ontario Court of Appeal has recently held that the discovery of facts following a mediation had the effect of extending the limitation period. This decision has an important impact on the limitation period for all claims, and particularly claims arising from building projects, in which the […]

Continue Reading
Page 2 of 2812345...1020...Last »