Thomas G. Heintzman, O.C., Q.C., FCIArb

Construction Law Canada

This website is intended to encourage discussion about recent developments in construction law in Canada.

The commentary in this website will relate to legislation and case law. Each item for discussion will be set out individually. The item will have a short description of the subject matter. Then, a lengthier discussion of the item will follow. The discussion is solely a matter of my personal view and opinion and does not constitute legal advice.

The discussion will generally follow the subjects addressed in my book: Heintzman & Goldsmith on Canadian Building Contracts (5th ed. Carswell).  Reference to that text will be made from time to time as “CBC”, that is Canadian Building Contracts. However, a broader range of subjects will be addressed in this site than those addressed in CBC.

I welcome any views about the commentary in this website and hope that a dialogue will develop about the distinctive aspects of construction law in Canada.

Continue Reading

When May An Arbitral Tribunal Correct Its Award?

Arbitrators are mortal. They may make mistakes in issuing their awards. In what circumstances may they correct an award? The scope of the authority of an arbitral tribunal to alter its award after the issuance of the award has been examined in a recent Scottish case – NKT Cables A/S v. SP Power Systems Limited, […]

Continue Reading

Supreme Court Of Canada Grants Leave To Appeal In Bond Notification Case

On March 9, 2017, the Supreme Court of Canada granted leave to appeal from the decision of the Alberta Court of Appeal in Valard Construction Ltd. v. Bird Construction Co., 2016 CarswellAlta 1584, 57 C.L.R. (4th) 171. This appeal will be of significance in determining the rights of contractors and subcontractors to receive, and the […]

Continue Reading

Recommendations To Amend Ontario’s Construction Lien Act

On April 30, 2016, a Report was delivered to the Ontario Government proposing amendments to the Ontario Construction Lien Act. This report may, in whole or in part, soon be implemented by the Ontario Legislature. For this reason, those engaged in the construction industry or construction litigation in Ontario must immediately become familiar with the […]

Continue Reading

Contract Limitation Clause Precludes Contractor’s Claim Over Against Designer

The limitation periods which apply to construction claims are difficult to sort out at the best of times. They are even more complicated when the limitation period applies to a claim over for contribution or indemnity. That situation arises when the owner sues the contractor and the contractor then seeks contribution or indemnity from another […]

Continue Reading

New International Commercial Arbitration Act Enacted In Ontario

On March 22, 2017, a new International Commercial Arbitration Act, 2017 came into force in Ontario (the 2017 ICAA). The 2017 ICAA is contained in Schedule 5 to the Burden Reduction Act, 2017, SO 2017, c. 2.. The 2017 ICCA replaces the existing Ontario International Commercial Arbitration Act, RSO 1990, c I.9 (the Old ICAA). […]

Continue Reading

Construction Contract Held To Mandate The Payment Of Extras

One of the most contentious issues in building contracts is mechanism to ensure that the contractor is guaranteed payment for extras, and that the owner is guaranteed not to pay for something that is not an extra. It would be simple to state these propositions in a building contract, but they usually aren’t there. However, […]

Continue Reading

Discovery Of Facts Following Mediation Impacts The Limitation Period: Ontario Court Of Appeal

In 625805 Ontario Ltd. v. Silverwood Flooring Inc., the Ontario Court of Appeal has recently held that the discovery of facts following a mediation had the effect of extending the limitation period. This decision has an important impact on the limitation period for all claims, and particularly claims arising from building projects, in which the […]

Continue Reading

Standard Form Contract To Be Given Plain Meaning, Not The Industry Meaning: Supreme Court Of Canada

In its recent decision in Sabean v. Portage La Prairie Mutual Insurance Co., the Supreme Court of Canada has held that words in a standard form contract used by the public should be given their plain and ordinary meaning, and not a different meaning that those words might be given by the industry or trade […]

Continue Reading

CRA Entitled To Priority Over Subcontractors To Trust Funds In Owner’s Hands

The Manitoba Court of Queen’s Bench recently held that the Canadian Revenue Agency (CRA) has priority over subcontractors and the bonding company in respect of holdback funds held by the owner in trust for the contractor. The decision in Manitoba Housing and Renewal Corp. v. Able Eavestroughing Ltd., once again underlines the impact of federal […]

Continue Reading
Page 1 of 2612345...1020...Last »