Thomas G. Heintzman, O.C., Q.C., FCIArb

A Subcontractor Recovers Against The Owner In Unjust Enrichment

A subcontractor who fails to register a construction lien faces an uphill battle in asserting a claim in unjust enrichment against the owner. That is because the owner will rely upon its contract with the contractor for any benefit that the owner has obtained from the subcontractor’s work. The owner will also assert that there […]

Continue Reading

How Does The Loss Of A Chance Apply To Damages For Breach Of A Building Contract?

Construction law practitioners must keep their eyes and ears open to the evolving case law in other areas of the law. That case law may have direct application to building contract issues. This fact is especially true for the assessment of damages. Because of the numerous contracts involved in a building project, a breach of […]

Continue Reading

When Does An Arbitral Award Contain An Appealable Question Of Law?

The Supreme Court of Canada has recently re-examined the issue of whether a statutory and contractual interpretation by an arbitral tribunal may be appealed. The court re-iterated the principle that arbitral awards are not appealable on a question of law when in reality the question is one of mixed fact and law. On this basis, […]

Continue Reading

What Amounts To An Effective Claim Under A Building Contract?

The Ontario Court of Appeal has recently allowed the appeal in the case of Ledore Investments Limited (Ross Steel Fabricators & Contractors) v. Ellis-Don Construction Ltd., 2017 ONCA 518. In doing so, it held that the arbitrator committed no reviewable error in deciding that the correspondence sent by Ellis-Don to its subcontractor did not amount […]

Continue Reading

May A Party Terminate A Contract For “Fundamental Breach”?

In the recent decision in R.P.M. Investment Corp. v. Lange, 2017 CarswellAlta 770, 2017 ABQB 305, the Alberta Court of Queen’s Bench held that a party to a contract may terminate a contract on the basis of a “fundamental breach” of the contract, in addition to the right to terminate the contract for repudiation. While […]

Continue Reading

Supreme Court Of Canada Grants Leave To Appeal In Bond Notification Case

On March 9, 2017, the Supreme Court of Canada granted leave to appeal from the decision of the Alberta Court of Appeal in Valard Construction Ltd. v. Bird Construction Co., 2016 CarswellAlta 1584, 57 C.L.R. (4th) 171. This appeal will be of significance in determining the rights of contractors and subcontractors to receive, and the […]

Continue Reading

Recommendations To Amend Ontario’s Construction Lien Act

On April 30, 2016, a Report was delivered to the Ontario Government proposing amendments to the Ontario Construction Lien Act. This report may, in whole or in part, soon be implemented by the Ontario Legislature. For this reason, those engaged in the construction industry or construction litigation in Ontario must immediately become familiar with the […]

Continue Reading

Contract Limitation Clause Precludes Contractor’s Claim Over Against Designer

The limitation periods which apply to construction claims are difficult to sort out at the best of times. They are even more complicated when the limitation period applies to a claim over for contribution or indemnity. That situation arises when the owner sues the contractor and the contractor then seeks contribution or indemnity from another […]

Continue Reading

Construction Contract Held To Mandate The Payment Of Extras

One of the most contentious issues in building contracts is mechanism to ensure that the contractor is guaranteed payment for extras, and that the owner is guaranteed not to pay for something that is not an extra. It would be simple to state these propositions in a building contract, but they usually aren’t there. However, […]

Continue Reading
Page 1 of 1512345...10...Last »