Tenders in Construction Projects – Which Limitation Period Applies?

What is the limitation period for the commencement of an action arising from a tender in a construction project?

If the owner is a municipality or other public body, does a limitation period in its incorporating legislation apply to the tender?  These were the questions recently faced by the Prince Edward Island Court of Appeal in Central Roadways v. City of Summerside.

In May 2008 the City of Summerside sought tenders for the resurfacing of city streets.  Two bidders, Central Roadways and another bidder, submitted tenders.  Central Roadways’ tender was the lowest, but on June 16, 2008 the City’s Council met and decided to award the contract to the other bidder, and advised Central Roadways the next day.

In November 2008, Central Roadways asked the City why its tender was not accepted and requested a copy of Council meeting minutes of June 16, 2008.  The City replied by letter and provided  a copy of the minutes but the minutes did not disclose any reasons why the other tender was accepted and not the tender of Central Roadways.

On February 20, 2009, Central Roadways commenced an action against the City.  The City brought a motion to dismiss the action on the ground that it was barred by the limitation period in s-s.46 (2) of the City of Summerside Act.

Section 45 and 46(1) of that Act provided that notice was to be given to the City in the case of damage sustained from unsafe conditions, or from nuisances or encumbrances, on City streets or sidewalks.  Section 46(1) then said that, except as provided in S. 46(1), all actions against the City were to be commenced within six months of the cause of action arising.

The City asserted that this limitation period applied to the claim arising from the tender, and the judge who heard the motion agreed.  But the P.E.I Court of Appeal reversed the decision.

The Court of Appeal examined the wording and history of the City of Summerside Act and concluded that the six month limitation period only applied to claims arising from City bylaws or claims relating to unsafe conditions or nuisances and encumbrances on City property.  Even though the word “all” in s. 46(2) was normally all-encompassing, it should not be so interpreted in light of these surrounding circumstances.

The Court of Appeal noted that the limitation period in P.E.I. for claims in contract is six years and that a limitation period of six months is a very different limitation period.  Since the shorter limitation period was found in a statute for the City’s benefit, it should be interpreted against the City in the event of any ambiguity.  The Court said:

“Interpreted to include all causes of action against the City, the very short six-month limitation period would seriously circumscribe the right of a person to commence any action against the City.  This being so, any ambiguity must be resolved in favour of a less restrictive limit on the time within which to commence an action.”

The Court of Appeal held that the claim by Central Roadways was in contract, since it arose from the alleged breach of its contract with the City inherent in its submission of a tender to the City’s invitation.   While there might be good policy reasons for the City to provide very short limitation periods for actions arising from slip and falls or other accidents on City streets,

“there is no valid policy reason why other actions against the City, like an action for breach of contract, should have the time for the commencement thereof limited to a very short six months…If the Legislature is of the mind that there are valid policy reasons for a shorter limitation period for the commencement of such actions against municipalities like the City, then it should express the policy more clearly in the Act  so as to specifically exclude these actions from the scope of the Statute of Limitations.”

This decision contains warnings about limitation periods relating to tenders.

The first warning is that a claim arising from a tender is a claim in contract and must be brought within the limitation period for a contract claim.  In addition, a tort claim relating to the tender must be brought within the limitation period relating to tort claims.

The second warning is this:  look for any limitation period contained in the tender documents. The tender documents may themselves contain a specific and shorter limitation period.  A shorter contractual limitation period may be permitted under the general limitation statute.  Thus, In Ontario, s.22(5) of the Limitations Act, 2002 permits the normal two year limitation period to be shortened in business agreements, but not consumer agreements.

And third, ensure that there are no other statutory limitation periods which may apply to the tender.  In Ontario, that is unlikely since s.19 of the Limitations Act, 2002 states that a statutory provision containing a conflicting limitation period is of no effect unless that provision is set out in the Schedule to the Limitations Act, 2002.  But if there is a limitation provision in another statute which is potentially enforceable, then depending on the origin and nature of that provision, the decision in the Central Roadways case may require that the limitation provision be read against the public body and only enforceable if it clearly applies to the tender.

Tenders – Limitation Period – Construction Contract – Actions – Breach of Contract – 

Central Roadways v. City of Summerside, 2011 PECA 4 (CanLII)  https://bit.ly/jnQhQk

Who Knew That Mary Carter Was Involved In Construction Law?

In Aecon Buildings v. Stephenson Engineering Limited, the Ontario Court of Appeal recently dismissed a construction law claim because a Mary Carter agreement was not immediately disclosed.

A Mary Carter agreement is a settlement agreement between a plaintiff and defendant in which the defendant remains an active party to the litigation and the claim also proceeds against other parties.  Since the defendant continues to participate in the action, the appearance is conveyed that the defendant is still liable to the plaintiff, contrary to the reality of the settlement.  For this reason courts have always insisted that a Mary Carter agreement be immediately disclosed to all parties.  But what happens if it isn’t?  The Ontario Court of Appeal faced that situation in this case.

The general contractor, Aecon, sued the owner, the City of Brampton, for damages due to the delay in the construction project.  The City blamed the consultant for the delay.  The consultant blamed the sub-consultants.

Before the action was commenced, Aecon and the City settled Aecon‘s claim on the basis that Aecon would only recover from the City the amount that the City recovered from the consultant.

While the settlement was effectively made before the action was commenced by Aecon against the City, it was reduced to writing the day after that action was commenced.  Once the action was commenced, the City claimed over against the consultant and the consultant claimed over against the sub-consultants.

Aecon and the City remained active parties in the litigation, but the settlement agreement was not immediately disclosed to the consultant or sub-consultants who only discovered it later through other sources and demanded that it be produced.

The Court of Appeal held that the delay in the disclosure of the settlement agreement amounted to an abuse of process, even though the disclosure did occur before the affected parties were required to plead.  The agreement had only been produced several months after its existence was discovered by the consultants and when it was specifically requested.

The Court said that the only way for it to control its own process, in order to ensure that Mary Carter agreements are immediately produced, was to dismiss the City’s claim against the consultant and thereby the further claims by the consultant against the sub-consultants.  Permitting the litigation to proceed without disclosure of the agreement rendered “the process a sham and amounts to a failure of justice” in the Court’s view.

This decision is a reminder of the drastic remedies available to the Courts if litigation is conducted unfairly.  While Mary Carter agreements are most often used in personal injury or medical malpractice actions, they can also be used to settle construction litigation.  When they are, the parties must be scrupulous to ensure that the agreement is immediately disclosed.  Otherwise, any further claims in the action may well be dismissed.

Aecon Buildings v. Stephenson Engineering Limited, 2010 ONCA 898 (CanLII)    https://bit.ly/dPjnqH

Construction Law – Claims – SettlementAgreement – Litigation – Champertous – Abuse of ProcessMotion

www.constructionlawcanada.com                                                    April 3, 2011