Construction Lien Act-Date of last supply

Construction Lien Act – Date of last supply of services and materials: The attendance by a paving reinforcement subcontractor at an off-site meeting to deal with the claim of that subcontractor and the main contractor does not amount to the supply of services and does not extend the lien period: Hugormark v. HMTQ, 2010 ONSC 7033. See CBC, Chapter 11, part 2(c).