Thomas G. Heintzman, O.C., Q.C., FCIArb

Is A Notice Of Intention To Recover Costs A Proper Notice Of Claim Under A Building Contract?

In Ledore Investments Ltd. v. Ellis-Don Construction Ltd., the Ontario Superior Court has recently held that a letter from a contractor to a subcontractor stating that “we intend to recover these costs from you” was a sufficient notice to the subcontractor to satisfy the notice provision of the building contract. Accordingly, the court set aside […]

Continue Reading

No Representation Clause Precludes Reliance On Pre-Contractual Representation

In Houle v. Knelsen Sand and Gravel Ltd., 2016 CarswellAlta 1582, 2016 ABCA 247, the Alberta Court of Appeal has recently held that a “no representation” clause precluded a party from relying on a pre-contractual representation to rescind the contract. Background Houle owned a parcel of land in which Houle believed there were substantial gravel […]

Continue Reading

Tort And Fraud Claims Fall Within Arbitration Agreement: Ontario Court Of Appeal

In Haas v. Gunasekaram, 2016 ONCA 744, the Ontario Court of Appeal recently held that claims in tort and fraud, and resulting claims to set aside the agreement between the parties, were within the jurisdiction of the arbitral tribunal under an arbitration agreement. Accordingly, the court action between the parties was stayed. This decision is […]

Continue Reading

Standard Form Contracts Are To Be Reviewed On A Standard Of Correctness: Supreme Court Of Canada

In, Ledcor Construction Ltd. v. Northbridge Indemnity Insurance Co, 2016 SCC 37, the Supreme Court of Canada has held that the interpretation of a standard form contract is a matter of law alone, and not a matter of mixed fact and law. Accordingly, it is not sufficient for a judge to arrive at a reasonable […]

Continue Reading

Is The Charge Or Lien Against The Holdback Separate From The Lien Against The Land?

Summary In the recent decision in Brook Construction (2007) Inc. v. Blackwood Contractors Ltd, the Newfoundland and Labrador Court of Appeal held that the charge against the holdback under s.12(5) of the Newfoundland and Labrador Mechanics’ Lien Act (the NL Act) is the same as, and “parasitic” to, the lien against the land. Accordingly, since […]

Continue Reading

Is A “No Oral Variation” Clause In A Contract Binding?

Summary In MWB Business Exchange Centres Ltd v Rock Advertising Ltd [2016] EWCA Civ 553 and Globe Motors Inc v. TRW Lucas Varity Electric Steering Ltd. [2016] EWCA CIV 396, the English Court of Appeal has recently held that a contractual provision stating that the contract may only be amended by a written document signed […]

Continue Reading

Faulty Workmanship Exclusion In A Builders’ Risk Policy Excludes Only The Cost Of Re-Doing The Faulty Work: Supreme Court Of Canada

In Ledcor Construction Ltd. v. Northbridge Indemnity Insurance Co., 2016 SCC 37, the Supreme Court of Canada has issued a definitive decision about the scope of the “faulty workmanship” exclusion in Builders’ Risk insurance policies. The Supreme Court has held that the clause only excludes coverage for the cost of re-doing the faulty work, and […]

Continue Reading

Lien For Work Done Before The Certificate Of Substantial Completion And Payment Of The Major Lien Fund Does Not Attach To The Minor Lien Fund

Summary In Chandos Construction Ltd. v. Twin Peaks Construction Ltd., a Master of the Alberta Court of Queen’s Bench has held that a lien for work done prior to the filing of a certificate of substantial completion and payment of the major lien fund does not attach to the minor lien fund. Background Chandos was […]

Continue Reading

Faulty Materials Or Workmanship Exclusion In Insurance Policy Does Not Exclude Resulting Damage: Ontario Court Of Appeal

Summary In its recent decision in Monk v. Farmers’ Mutual Insurance Company (Lindsay), the Ontario Court of Appeal has held that the exclusion for faulty materials or workmanship in an owner’s property insurance contract does not exclude the insured’s right to recover the resulting damage that the faulty materials or workmanship has caused. This is […]

Continue Reading
Page 1 of 2512345...1020...Last »